The Tanzania Railways Corporation plans to start testing the standard gauge railway electricity systems over three months, run by four sub-stations along the completed 300 kilometres stretch between Dar es Salaam and Morogoro.
The four sub-stations are 50km apart, with 19 transformers, and the test will be done in two main stages — the unit test and the component test.